Septic wet weather testing in Tehama County is a set of groundwater readings taken in observation wells during the rainy season, and it only counts after about 80 percent of normal rainfall has fallen. Outside the Anderson Cottonwood Irrigation District, readings run about monthly from January 1 to April 30, so a lot that needs it can't get a septic design approved until late spring at the earliest.
That timing is the whole story for most people. If the county says your lot needs wet weather testing, you've just been handed a calendar you don't control. Here's when Tehama County requires it, how it works, and what we'd do to keep a build from sliding a full year.
What the test is actually measuring
A leach field works because soil filters effluent before it reaches groundwater. If the water table rises too close to the trench bottoms in winter, that filtering doesn't happen, and the field can fail.
So the county wants to know the seasonal high water table, meaning the highest point groundwater reaches when the soil is fully soaked. You can't see that in August. A test pit dug in dry weather might look like perfect, deep soil, then fill with water by February.
Tehama County's Sewage Disposal Standards (Chapter 5) set the required separation between the trench bottom and that seasonal high water table:
| Lot size | Minimum separation, trench bottom to seasonal high groundwater |
|---|---|
| Less than 10 acres | 5 feet |
| More than 10 acres | 3 feet |
Five feet is a lot on flat valley ground. Parcels around Corning and Los Molinos with clay layers or shallow water are where the county asks for proof.
When Tehama County requires wet weather testing
Not every lot gets this requirement. It's triggered by what's found on or near the parcel. Under the county standards, the height of seasonal high groundwater has to be determined by wet weather testing when any of these show up:
- Vegetation that tolerates or signals a high water table, on the parcel or nearby. Think willows or cattails in a low swale.
- High groundwater has already been found in the vicinity.
- The test pits show cracked or creviced formations with no clear top to the water table.
- Other conditions or historical data make dry weather readings unreliable.
- Free water is seeping into the test pit.
Each lot needs at least one test pit, at least 2 feet wide and 8 feet deep, with the soil profile logged by a qualified person and witnessed by Tehama County Environmental Health. That pit is usually where the question gets settled. If the soil log comes back clean and nothing on the list above applies, you may not need wet weather testing at all.
If you do, it's not something you or your excavator can sign off on. The standards require the testing to be done by or under the supervision of a registered civil engineer, registered geologist, registered environmental health specialist, certified engineering geologist, certified soil scientist, or an approved testing lab. Our part is the dirt work around it.
How the testing works, step by step
The county's Bulletin #1, published inside the same chapter, lays out how the monitoring wells should be built and read.
Drill the wells while the ground is dry
Observation wells are drilled to 10 feet. The bulletin says to use a drill, not a backhoe, because a backhoe tears up the soil around the hole and the well ends up reading the disturbed hole instead of the real soil profile. Backhoe-dug wells tend to show water standing higher than it really is, which can fail a lot that should have passed.
The bulletin also says to complete the hole in summer while the soil is dry. Drilling into saturated soil smears the walls of the hole, which keeps it from draining and again reads high. The top 3 feet get sealed with concrete so surface water can't run down the outside of the casing. A bad seal is the main cause of erratic, unnaturally high readings.
Start reading before the soil saturates
Here's a detail that matters right now in November. The bulletin notes that saturation usually happens after about 9 to 12 inches of cumulative rainfall, counted from around October 1. Once the season total hits 9 inches, the wells should be read at least every 3 days until saturation. After that, readings go weekly, no matter where the water sits, until the well goes dry. If it rains again after that, readings start back up.
The standard itself sets a separate bar for when readings count: actual measurements during maximum soil moisture, after 80 percent of normal precipitation has fallen. Outside the A.C.I.D., the default is about monthly measurements from January 1 to April 30, unless Environmental Health directs otherwise. Your engineer will tell you which schedule your lot is on.
The irrigation district exception
Inside the Anderson Cottonwood Irrigation District, it's irrigation water, not rain, that pushes groundwater up. So for land where A.C.I.D. water is the cause of the monitoring, the county flips the calendar: monthly readings from May 1 through August 31. If your parcel is in that district, a winter test may not be the one that counts.
Results go to Environmental Health with a scaled plot plan, and the Director can throw out any test that doesn't represent the parcel's real soil. One more reason to build the wells the way the bulletin says.
How long does it add to a project?
Plan on a season. If a lot needs testing, the septic design and permit can't really move until the spring readings wrap up, and that's before any trenching starts.
A dry winter is the real risk. If rainfall never gets to 80 percent of normal, the readings may not satisfy the standard. Shasta County's published standards spell out what happens next door: if seasonal rainfall from December 1 to the April 30 cutoff doesn't exceed 80 percent of normal, testing continues the next year, or the site can be evaluated by mathematical modeling. Tehama's Bulletin #1 is written around that same modeling approach, which is why it stresses taking lots of readings. Ask your engineer early whether modeling is an option for your lot if the year comes in dry.
A one-year slip is a real possibility, so we'd treat wet weather testing as the first item on the schedule for any rural build on flat ground, ahead of the house plans.
What we'd do on a lot that might need it
If you're looking at a parcel with any of the warning signs above, this is the order we'd go in:
- Dig the test pit early, ideally late spring or summer, so you know where you stand while there's still time to drill wells in dry ground.
- Get the engineer or REHS on board before you close on the land if you can. Their read on the pit tells you if you're buying a one-season delay.
- If wells are needed, have them drilled and sealed in summer, before October rains start counting.
- On a parcel over 10 acres, look for the highest workable ground. The separation drops to 3 feet there, and a little elevation goes a long way.
- Keep your grading and pad work in mind. Fill isn't usable disposal material unless it's engineered for sewage disposal and approved by Environmental Health, so don't let anyone push spoils across your future leach field area.
That last one comes up more than you'd think. A pad gets cut, the extra dirt lands on the flat spot that looked unused, and that was the only place the field could go.
If it's already raining and nothing's been drilled, talk to your engineer this week about whether a well installed now will be accepted. It's Environmental Health's call, not ours, and we'd rather you hear the honest answer in November than in April.
Where Walberg, Inc. fits in
We don't run the groundwater test. That belongs to the engineer or REHS and the county. What Walberg, Inc. handles is the excavation side: digging test pits, then installing the septic system once the design is approved, along with any grading or house pad work on the same parcel. We've been owner-operated and working Northern California ground since 1999, and we hold CSLB License #898860.
You can read more about our septic system installation and excavation work, or see the other services we cover across Tehama County. Tehama County's Local Agency Management Plan lays out the county's broader septic program.
Common Questions
What is wet weather testing for a septic system?
Wet weather testing is a series of groundwater readings taken in observation wells during the rainy season to find the seasonal high water table. Tehama County uses it to confirm there's enough separation between the bottom of the leach field trenches and groundwater. That separation is 5 feet on lots under 10 acres and 3 feet on lots over 10 acres.
When is the wet weather testing season in Tehama County?
Outside the Anderson Cottonwood Irrigation District, readings are taken about monthly from January 1 to April 30, after about 80 percent of normal rainfall has fallen. Inside the A.C.I.D., where irrigation raises groundwater, monthly readings run May 1 through August 31. Environmental Health can set a different schedule based on local conditions.
Do all septic permits in Tehama County need wet weather testing?
No. It's required when there are signs of high groundwater, such as water-loving vegetation or seepage in the test pit, or when the soil profile doesn't show a clear top to the water table. Many lots with deep, well-drained soil and a clean test pit log never need it.
What happens if it's a dry winter?
If rainfall doesn't reach about 80 percent of normal, the readings may not meet the standard, and testing can roll into the next wet season. Shasta County's standards allow mathematical modeling as an alternative in that case. Ask your engineer whether modeling applies to your Tehama County lot before the season ends.
The bottom line
If your lot might need wet weather testing, the test pit is the most useful hole you'll dig on the whole project, so get it dug before you commit to a building schedule. Then line up the engineer, drill the wells in dry ground, and plan the septic install for after the spring readings. When you're ready to dig the pit or put in the system, request a free estimate and we'll take a look at your site.