RV pad cost in Northern California is driven mostly by the dirt work and the hookups, not the rock on top. A compacted base rock pad is the cheapest pad that lasts, concrete usually costs several times as much for the same footprint, and running utilities out to the pad can cost more than the pad itself. For a number on your property, request a free estimate and tell us the RV length and where your power and septic are.
This call comes in every late fall. Someone parked a fifth wheel on a dirt spot behind the shop in October, the first storms rolled through, and now the jacks are sinking and the tires cut ruts every time it moves. Walberg, Inc. builds RV pads for property owners around Corning, Red Bluff, Chico and Redding, and the fix is almost always the same: get the soft dirt out, put down a real base, and give the water somewhere to go.
What goes into the price of an RV pad?
Every pad has the same parts. Your lot decides how much each one costs.
| Cost factor | What it covers | What pushes it up |
|---|---|---|
| Clearing and stripping | Pulling brush and topsoil off the footprint | Stumps or old buried concrete |
| Cut, fill and compaction | Making the subgrade flat and solid | A sloped lot, or soft clay that has to be dug out |
| Base rock | Compacted Class 2 or recycled base | A deeper section for a heavy motorhome or poor soil |
| Drainage | A crown or slope, sometimes a ditch or culvert | A low spot that catches runoff from the rest of the lot |
| Access | A path from the driveway wide enough to back in | A long run or a culvert crossing |
| Hookups | Trenching for power, water and a sewer or septic tie-in | Long distances from the panel or house, rock in the trench |
| Concrete (optional) | Forms, rebar and the pour | Slab thickness and how far the truck has to reach |
The biggest swing on most rural lots is the subgrade. Decent ground strips and compacts fast. On the valley clay around Corning and Gerber, the soil turns to grease when it's wet, and we may have to dig out the soft layer and bring in fill before any rock goes down. That's the difference between a pad that's still flat in five years and one that's rutted by March.
How big should an RV pad be?
Size the pad for the rig you'll own next, since people trade up. A good rule is the RV length plus about 10 feet, and at least 12 feet wide. Go wider if you have slide-outs or want room for chairs and a table. A 12 by 40 foot pad fits most travel trailers and a lot of fifth wheels.
Here's the rock math on that 12 by 40 pad at 6 inches deep. That's 240 cubic feet, or about 9 cubic yards in place. Compacted base rock is heavy, so plan on roughly 15 to 17 tons, plus a little more for the approach.
Plenty of people figure they'll order a load and spread it themselves. You can. But pads don't fail because of the rock. They fail because nobody compacted the base, or the dirt underneath was soft to begin with.
Should the pad be rock or concrete?
For most RVs parked on a rural lot, compacted base rock is the right call. It drains and it's easy to fix. It also costs a fraction of what a slab does. If a corner settles, we add a few yards and recompact. Try that with concrete.
Concrete earns its keep in a few situations:
- You want an RV cover or carport over it, and the posts need footings anyway
- The RV sits for years without moving and you're tired of stabilizer jacks sinking
- The pad doubles as a work area where you'll roll a floor jack
- An HOA or a lender requires it
Recycled base rock works fine under an RV, and our concrete and asphalt recycling yard sells it. It compacts tight when it's placed at the right moisture. If the pad might become a shop floor someday, we'd talk through a slab before you put rock down twice.
Do you need a permit for an RV pad?
The pad itself usually isn't the permit problem. Tehama County Public Works sorts grading permits by volume, and the smallest category is under 250 cubic yards. A typical RV pad is a fraction of that. A pad close to a seasonal creek is a different story, so we check where the water runs before we dig.
What catches people is the RV, not the rock. Tehama County treats living in an RV differently from storing one. Under the county code we've read (Chapter 17.86), occupying an RV for 30 days or more takes a temporary occupancy permit, and the conditions are specific:
- The property needs a house or a manufactured home on a permitted foundation, or an active building permit for one.
- Only one RV can be permitted.
- The RV has to sit at least 10 feet from other structures and 20 feet from property lines.
- No permanent power under that temporary permit, and no renting it out.
- Any well or septic on the site plan needs written approval from Environmental Health.
The county's Administrative Use Permit checklist asks for a site plan showing the parking area, its distance to every property line, the septic tank and leach field, the sewer hookup and cleanout, and the water connection. It's the same layout we need to price the job, so it's worth drawing either way.
Storage is simpler. The code allows an unoccupied RV on a lot with a residence as long as it's disconnected from its hookups. If you lost a home in the 2024 Park Fire, Tehama County also adopted an urgency ordinance (No. 2140) with separate temporary housing standards for displaced residents, so ask Planning whether it still covers your parcel.
Rules change, so call Tehama County Planning at (530) 527-2200 with your parcel number before you build. Butte and Shasta counties, and the cities, have their own rules.
What about power, water and sewer?
Hookups are where budgets go sideways, mostly because of distance. A pad 30 feet from the house and one 300 feet out by the barn are very different trench jobs.
We dig the trench and lay the conduit through our trenching and conduit work. A licensed electrician pulls the wire and sets the 30 or 50 amp pedestal under an electrical permit. California law requires a call to 811 at least two working days before anyone digs, and on rural lots we still find private lines nobody marked, so we hand-dig near anything that looks suspicious.
For sewer, you have two honest options. Tie into the septic with a proper cleanout and Environmental Health's sign-off, or skip the line and haul to a dump station. Hooking an RV to a septic system that's already marginal is a fast way to find out it's marginal. If your tank and leach field are old, have them looked at first. Our septic systems team can tell you whether they'll take the extra load.
Can you build an RV pad in the winter?
Sometimes. It depends on the ground more than the calendar. Gravelly soil and decomposed granite up in the foothills can often be worked a few days after a storm. Valley clay can stay too wet to compact for weeks at a time from December through March.
We'd rather wait for a dry stretch than put rock on mud. Rock pushed into wet clay pumps up through the base as soon as the RV sits on it, and you end up paying for the pad twice. If your trailer is sinking now, get it up on boards and save the real pad for a dry window. Use the winter to get the estimate and county paperwork done.
When an RV pad isn't the right call
If the plan is for a family member to live on the property for the long haul, an RV may be the wrong tool. The no-permanent-power condition on the temporary permit alone makes it a poor fit for year-round living in Tehama County. A pad for an ADU or a manufactured home costs more up front but solves the problem for good, and it's the same house pad and driveway work we do all the time.
Common Questions
How much base rock do I need for an RV pad?
For a 12 by 40 foot pad at 6 inches deep, figure about 9 cubic yards in place, or roughly 15 to 17 tons of compacted base rock. Order a little extra for the approach and any low spots.
Is gravel or concrete better for an RV pad?
Compacted base rock is better for most rural RV pads because it drains well and costs much less. Concrete makes sense under an RV cover with footings, or when the RV will sit for years without moving. Avoid loose pea gravel. It's round, so it rolls under tires and jacks and never locks up.
Can I live in an RV on my property in Tehama County?
Only with a temporary occupancy permit if you'll be in it 30 days or more, under Tehama County Code Chapter 17.86. The property needs a permitted house or manufactured home first. Only one RV is allowed, and it has to sit 10 feet from structures and 20 feet from property lines. Confirm the current rules with Tehama County Planning at (530) 527-2200.
How thick should an RV pad be?
Most rock pads get 6 inches or more of compacted base over a firm subgrade. Soft clay may need the bad material dug out and replaced first. The subgrade matters more than the thickness of whatever goes on top.
Do I need a permit to run power to an RV pad?
Yes. A new RV pedestal is new electrical work, and in California that takes an electrical permit pulled by a licensed electrician. The 811 call is required by law before anyone digs the trench.
The bottom line
The rock is the cheap part. Put your money into the subgrade and the drainage, and decide early whether the RV is for storage or for someone to live in, because that changes both the county rules and the hookup plan. If you're in Tehama County or anywhere around Corning and Chico, send us the RV length and a rough sketch showing where the power and septic are, then request a free estimate. We'll tell you if your ground can be built on this winter or should wait for spring.